1.11 MW of PV panels were installed on 11000 square meters to generate electricity under the “Wheeling” concept.
The plant consists of 4200 units of Jinko “tier 1” polycrystalline panels (265 Wp each), 42 units of ABB 27.6 kW inverters and a state of the art aluminum mounting structure made by the famous German manufacturer “Schletter”.
Wathba Energy, a Jordanian pioneer EPC contractor, was awarded this project after a thorough pre-qualification process that included technical experience, financial capability, equipment quality, commitment to safety measures and commitment to deadlines.
Realizing the 1.11 MW project was a challenge due to the topography of the land, accessibility to the site and Medium Voltage (MV) connection limitations according to the new MV grid code.
Wathba Energy has completed all the infrastructure works, auxiliary works, civil works, mechanical works and electrical works on time and according to the Jordanian regulations and best practices in the field.